St.
Louis Downtown Airport's Tower construction is substantially complete and final equipment installation is underway. The tower is scheduled to become operational on the morning of June 26, 2008 with all new ATC frequencies in use. ATIS: 121.45 (replaces 127.85) Scroll down to see our progress. JULY
17, 2006 August 9,
2006 August 15,
2006 August 22,
2006 August
29, 2006 Sept.
12, 2006 Sept.
16, 2006 Sept.
21, 2006 Oct.
3, 2006 Nov. 2, 2006:
We've reached cab height! Nov. 17,
2006 Nov.
22, 2006: The Cab is being constructed on the ground. Nov. 29,
2006: Cab progress continues. The cab is being
built on the ground and will be lifted to the top in mid-December.
Dec. 4:
Soybeans have been replaced by snow but construction continues ahead
of schedule. Dec.
5: The exterior shaft walls begin to enclose the
tower's skeleton. Dec.
20: We're
ready to set the cab on top on Jan. 2nd Jan.
2: The cab is lifted to the top of the shaft.
Feb. 12:
Project now 57% completed with roofing, elevator, and interior
work underway. Aug. 17: Final interior touch-up
painting underway. Views
from the 90 ft. level (48 ft. from the top.)